Generation at Maximum Demand total of Previous Day 530 MW | Viva Exam Notice (DM-HRM & DM-FINANCE) | Written Exam (Apprentice-Technical) Postponed
Plant Status
DESCRIPTION
UNIT-1 UNIT-2 UNIT-3 UNIT-4 UNIT-5 GT-2 50 MW GE GT-225MW Total
Date of
Comm.
17-Jul-70 08-Jul-70 17-Dec-86 04-May-87 21-Mar-88 23-Mar-86 01-Mar-11 20-Apr-15
Installed
Capacity (MW)
64 64 150 150 150 56 53 150 837
Present
(De-rated)
Capacity (MW)
64 64 150 150 150 40 53 150 821