Plant Status

DescriptionUNIT-3 UNIT-4 UNIT-5 50 MW GE 225MW CCPP Ashuganj CCPP (South) Ashuganj 450MW CCPP (North) 200 MW Modular Total
Date of Commissioning December 17, 1986 May 4, 1987 March 21, 1988 March 2, 2011 April 20, 2015 July 18, 2016 June 11, 2017 May 8, 2016
InstalledCapacity (MW) 150 150 150 53 223 382 389 195 1692
Present Capacity: Net Output (MW) 129 138 128 46 222 359 360 195 1577