"শেখ হাসিনার উদ্যোগ, ঘরে ঘরে বিদ্যুৎ"

<<< পূর্বের দিনের সর্বোচ্চ বিদ্যুৎ উৎপাদনঃ 890 MW " >>>
Ongoing Projects

1. Ashuganj 450 MW CCPP (North) Project
Project Financed   : ADB (47%), IDB (41%), GOB (10%) & APSCL (2%)

Project Highlights:  

Name of the Bid: Construction of Ashuganj 450 MW Combined Cycle Power Plant (North) on Turnkey Basis
Bidding Procedure: Two stage bidding (ADB)
Net Output: 450?20% MW
CCGT Configuration: Single Shaft or Multi shaft (not more than 2:2:1 for Multi Shaft)
Completion Period: CCGT- 30 months from contract effective date
Plant Life: 25 years

Objective:  

a. To narrow the ever increasing gap between demand and supply of electricity through gas based low-cost generation in the north-east zone of the country.
b. To meet up increasing power demand in the country by adding local generation.
c. To increase the power generation through utilization of countrys natural gas resources available nearest to the proposed power plant site with requisite pressure.
d. To accelerate the economic development of the country by adequate and reliable power generation and to support the planned target of power demand.
e. To overcome the present generation shortage by increasing generation and to minimize load shedding.
f. To enhance the stability and reliability of the national grid system and reduce the transmission loss by local generation.
g. To increase energy efficiency of power generation.

Estimated cost of the project :  Estimated (Lakh Taka): Total : 340,002.50 (Local/GOB : 35,271.65; F.Ex./PA :299,604.60; APSCL: 5,126.25)
Date of ICB floating:  July 22, 2012
Date of tender opening:  July 3, 2012
Notification of Award (NOA):  November 17, 2013
Notification of Award (NOA):  November 17, 2013
Acceptance of NOA:  November 19, 2013
Contract Agreement:  December 1, 2013
Contractor:  The Consortium of Tecnicas Reunidas S. A. & TSK Electronica Y Electricidad S. A.
Commencement of early works:  02 April, 2014
Date of LC opening:  23 December, 2013
Date of commencement:  02 April, 2014
Date of completion:  03 June, 2017
Commercial Operation Date:  01 June, 2017 (RCOD)
Project Director:  Engr. Kshitish Chandra Biswas, Email: [email protected]
Physical Progress :  

Project Physical Progress: 59.41%
EPC Physical Progress: 99.56%

  • GT First Fire was achieved on 10.01.2017 and Firs Synchronization with the grid was achieved on 12.01.2017.
  • GT (Open Cycle) Performance Test was completed on 26.01.2017.
  • Commercial Operation Test of Simple Cycle Has been completed on 13th February 2017.
  • Steam Blowing is completed and the Combined Cycle Commissioning activities have started.
Financial Progress:  

Project Financial Progress: 56.26%
EPC Financial Progress: 79.56%