SL. No. Description of the Project Construction Period Remarks
01. Turbine blade of Unit-3 Change in this year. After end of this work 45MW generation will increase. December 2010 APSCL own funding
02. Rehabilitation & Modernization of Unit 3, 4 & 5 for reliable power generation 150 MW each unit for next 15 years. 2000-2011 Financed by KfW-German, DRGA- Japan & GOB
03. 50 MW Gas Engine Power Plant March 2011 APSCL own funding
04. 1.0 MW Solar Panel Installation 2010 - 2012 APSCL own funding
05. 150 MW Combined Cycle Power Plant (replacement project) 2010 - 2013 Searching finance
06. 450 MW Combined Cycle Power Plant (replacement project) 2010 - 2013 Searching finance
07. To re-powered Unit # 3, 4 & 5 by installing three GT units about total 100 MW capacities. 2010-2014 Searching finance